I just wanted to activate ECM for Routing i.e., when ever i want to do any changes in routing change number is mandatory.

I know the process to activate ECM for Routing changes but i have a requirement that, i wanted to activate change number only WHEN WE WANTED TO DO CHANGES ONLY FOR STANDARD VALUES but not all (viz. changing in Text/work center/lot size etc etc)

Is there any possible ways to cater the requirement???

Pls let know. Thanks in advance.

Rgds,

V KUMAR

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 28, 2015 at 12:58 PM

    Dear V Kumar,

    ECM will work for tracking the changes in BOM , Revision level, Task list changes

    but as per your requirement you are asking ECN is mandatory for STANDARD VALUES

    hence please make the below configuration

    OP5A--> PP/PI/QM Task List :Operations screen

    Standard value code make as a Required..

    hope it may work for your requirement

    Regards,

    Venkatesh..