Maintenance plan - Completion requirement set indicator standard on

Hi all,

On the preventive maintenance plan I would like to set the completion requirement indicator standard on.

Is there a possibility to do this in customizing? Or another way?

I do not want to work with user exit (set the completion indicator on saving the preventive maintenance plan) because the user should be able to uncheck the indicator.

Thanks,

Laura

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    Oct 28, 2015 at 04:08 PM

    Hi Laura,

    you can try use this ABAP GuiXT Function module

    which activate and generate the GuiXT script for user group or for all users , Function can be called from enhancement in include LIWP3F1S ,

    it provide the default option so the user can uncheck the completion check box.


    Regards,

    Ziv


    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks all for the replies.

      It's what I was afraid of: without development, user exit or GuiXT it's not possible to set this automatically active. Your proposed solution will be checked at the customer.

  • Oct 28, 2015 at 12:58 PM

    Laura

    Is this for you only, or do want some control on who gets this field defaulted?

    Also have a look at transaction variants (SHD0).

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 28, 2015 at 09:48 AM

    Hello Laura,

    The solution it's User exit,

    Regards,

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 28, 2015 at 10:15 AM

    Hello Laura,

    You requirement can be tried through implicit enhancement in the program SAPLIWP3. Field name is CALL_CONFIRM.

    OR

    through GuiXT for individual users.