Former Member

how to make a material be able to explode 2 bom at same time

Hello,

My scenario is, we have 2 finished goods A and B, they all are using same semi-finished goods S1, but this S1 has 2 versions of bom, one is component R1, and another is component R2. now how to let now A it extract raw material R1, and B extract R2. I tried explosion number, but it doesn't work.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Oct 28, 2015 at 09:31 AM

    Hello,

    It is not possible with standard BOm scenario... You have to Variant Configuration. Instead of Making two BOM for S1, you make 200% BOM by adding both then items in same BOM . Then based on Characterisitc of A , it would select R1 material & Similarly for B would R2

    This is confirgurable BOM scenario. Many things to do activate , Class < characterisitc , Object dependency etc,

    Best Regards,

    Jatin

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 29, 2015 at 04:17 AM

    Hi,

    You provided two options of BOM to the System for making S1. Selection is been made based on either Order Qty, Order Date or Production Version.

    In MRP 4 View a field called BOM Selection Method controls this functionality.

    Select BOM based on Parent material number is not possible in case of normal item. Only KMAT material type can full-fill your requirement.

    Thanks With Regards,

    Dinesh Kumar V.