Logic behind requirement type change in sale order change mode.

Hi Everyone

I have came across a confusing behavior of system which I'd like to bring in your notice and get some input. I am not able to understand why system is doing this.

This is MTO scenario and we create sale order using ZMM requirement type. In Go Live users uploaded some wrong master data due to which system determined wrong requirement type in sale order. When I analysed, I came to know that this is because of strategy group in MRP3 view. I deleted strategy group from MMD and tried to change requirement type in sale order. Here I found that system is allowing to change requirement type for some items. Others were in grey mode.

I replicated the scenario in DEV and tried to understand why and when we are allowed to change it in VA02 but I am not able to understand the logic. Could anyone of you make me understand the logic that why and when system allow us to change requirement type in sale order change mode VA02 in MTO?

For reference check below screen where master data and all settings are same for both materials but system is allowing to change it only for one material.

Thank$

Capture.JPG (96.2 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Oct 28, 2015 at 09:47 AM

    Hi Mozzam,

    Please check and update is there any subsequent document exist for the first& second line items of the sales order in the above mentioned screen shot.

    Thanks,

    Krishna.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 11, 2016 at 08:27 AM

    Hi Moazzam,

    Have you got the answer to your query. I am facing the same problem where I am not able to change the material and requirement type in one order where as in another order i can change the Material and req type. Both the order types are different.

    The req type detemined are different in both the SO.

    But both the materials are same with same MM setup.

    Could you please help

    Regards,

    Jagjeet

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 28, 2015 at 12:37 PM

    Most probably for the second material the production order is not generated (yet).

    At the moment I can think of only a few possible reasons in a standard system when the field is greyed out - subsequent documents, rejection reason, delivery block with confirmation reset, credit block (because it should also block quantity confirmation). Because most of these work at document save, for newly added items you still can change the requirement type before saving.

    In case the orders in your PRD environment already have production orders generated, I am afraid this would be a challenging task.