Issue in roll up values in Evaluation

Hi Team,

In my scenario, we are creating the Portfolio Item which in-turn creates C-Project automatically. Then we link the Project Phase to WBS Element of R/3 using OBJECT LINK (as this WBS will hold the Planning & Actual cost from logistic modules).

Please not we are not doing any planning in C-Project although we have activated the FI integration and done the necessary configuration in Project Management.

I have two question over here :-

1. How can I bring Plan and Actual cost of PS WBS back to C-Project Phase?

2. When I'm running evaluation (Costs and Revenues of Linked Objects) it dose not roll up the values to the Phase and PD of c-project. Is I'm missing something?

Appreciate your help.

Thanks

Gaurav

Capture.PNG (13.6 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Oct 28, 2015 at 06:44 AM

    Hi Gaurav,

    1) Assumption is that when you use c projects for planning is done in c project and data flows to SAP Ps projects. I don't think there is two way flow of  data between cprojects and ps projects.

    2)  Please go thorough thiss link , let us know if you still have problems.

    Evaluations - SAP Portfolio and Project Management - SAP Library

    Thanking you

    Vengaiah