on 10-28-2015 6:23 AM
Hi Team,
In my scenario, we are creating the Portfolio Item which in-turn creates C-Project automatically. Then we link the Project Phase to WBS Element of R/3 using OBJECT LINK (as this WBS will hold the Planning & Actual cost from logistic modules).
Please not we are not doing any planning in C-Project although we have activated the FI integration and done the necessary configuration in Project Management.
I have two question over here :-
1. How can I bring Plan and Actual cost of PS WBS back to C-Project Phase?
2. When I'm running evaluation (Costs and Revenues of Linked Objects) it dose not roll up the values to the Phase and PD of c-project. Is I'm missing something?
Appreciate your help.
Thanks
Gaurav
Hi Gaurav,
1) Assumption is that when you use c projects for planning is done in c project and data flows to SAP Ps projects. I don't think there is two way flow of data between cprojects and ps projects.
2) Please go thorough thiss link , let us know if you still have problems.
Evaluations - SAP Portfolio and Project Management - SAP Library
Thanking you
Vengaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vengaiah,
Thanks for your prompt reply,
On Point one, the actual moves back from PS to C-Proj so I believe there must be a way to have two way communication for Plan Cost.
On Point two, I did follow the instruction as per the SAP Help Library and Config Guide, but no luck. Even when i try to aggregate the values still it does not roll up to Phase and this is happening for Dates also.
I'm not sure what the silly thing I'm missing here.
Hope to get some answer soon.
Thanks
Gaurav
Hi Gaurav,
1) When you book timesheet using cats and account assignment is cproject project and task, Then actual hours will transferred to cprojects. If you clearly observe. Plan costs flow from cProjects to PS- Projects. Actuall costs flow from Cats to cprojects. But you don't have Actuals going from cProjects to PS . I see clearly a on side flow of data either Plan costs or Actual costs.
2) Can you recheck your config once again.
Thanking you
Vengaiah