Error while creating Production order for Raw material

hi. i am not able to create production order TCode : CO10 for raw material for which MRP type is P1, since i am getting error like work scheduling is not maintained. please let me know how to proceed on this

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Oct 28, 2015 at 10:43 AM

    Hello

    Your system behavior is correct. The definition of raw material is a material that can only be supplied externally, therefore, it should not be possible to create a production order for this material type.

    It means that you cannot create the tab work scheduling for this material type. In addition, the procurement type is always "F - External procurement" and it cannot be changed.

    If you need to create a production order for this material, it means that it is a semi-finished material (HALB) instead of a raw material.

    Regards
    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 28, 2015 at 01:07 PM

    Hi Yeshaswini,

    only In house materials has the work scheduling view

    the work scheduling view has a production scheduling profile and production scheduler

    without this view you will be not able to create production order or convert planned order to production order

    NOTE : work scheduling view will come only if the material type semi finished and Finished components

    Regards,

    Venkatesh..

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 11, 2015 at 05:51 AM

    Thank you all for the clarification