alternate bom component field unable to edit in Subcontract PO

Feb 03, 2017 at 09:51 AM

71

avatar image

Dear Experts,

During creation of Subcontracting PO, we need to display the Alternate BOM component, but that field under extras is geyed out then how to change the component based on Alt bom.

Product version is working for two different vendors not working for same vendor.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Jürgen L
Feb 03, 2017 at 12:54 PM
0

I don't think there is any option to do in the PO. If you want make use of another alternative BOM then you have to exchange the product version in the info record prior to creating the PO

Read also OSS note 858239 - The Subcontracting Info Record as there might be an option if you start from a requisition

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Dear Mr.Jurgen,

The product version concept working fine, for the info record with different vendors, but my scenario is one info record but different alt bom, in this case though the product version exists the req Alt bom component not updating.

0

please read the OSS note.

0