on 10-27-2015 3:04 PM
The requirement is to publish the Header material as well as components, as planned order to ECC from APO.
Header material and components all have procurement type E, and MRP type X0.
Once published; in ECC, they will be changed to manufacturing orders or purchase orders.
For a test, I did it for header material, changed it in product view (rrp3) (from snp planned order to planned order) published it, it is showing in ECC as planned order.
However when I am changing the components in rrp3 from SNP planned orders, it is changing them to purchase reqs.
component = dependent demand (BOM)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
S,
The requirement is that business wants these dependant demand to come to ECC as planned orders and there they decide whether to change it to manufacturing orders or production orders
This is bizarre. Dependent demand is...demand. Planned orders are....supply. Why would the business wish to see dependent demand created in ECC as 'supply'?.
Normally, one sends SNP Planned orders over to ECC as ECC Planned orders. The SNP planned order is replicated in ECC. The ECC planned order will in standard create 'supply' for the header materials; and will also automatically create dependent demand for all of the component materials in ECC that matches the dependent demand you see in SCM for the component materials.
Are you saying that SNP Planned order dependent demand is not going to ECC (which is standard functionality); or are you saying that you DON'T want this standard behavior?
Best Regards,
DB49
Thanks for the reply. May be i was not clear enough in my explanation, The requirement is that demand for a particular component (semi finish )which itself has a bom in ECC under it to be planned in APO and publish to ECC as planned order. The procurement type for this component is X. When I am changing the SNP planned order to planned order to be replicated to ECC. It is changed to purchase reqs rather than planned order.
Normally, one sends SNP Planned orders over to ECC as ECC Planned orders. The SNP planned order is replicated in ECC.
........................................
Can you tell me how that can be done ? For a component. This component is in a BOM of a material and it also has it own BOM under it. Many thanks
S,
When I am changing the SNP planned order to planned order to be replicated to ECC. It is changed to purchase reqs rather than planned order.
What does this mean? Exactly what are you doing in SCM? Why are you 'changing' the SNP Planned order?
SNP Planned orders in Version 000 will automatically be replicated in ECC if you have turned on publishing (/SAPAPO/CP1). Assuming all your Integration models are in place and activated, the planned orders will bring across both the supply portion for the header and the demand portion for the components.
Exactly how are you creating your SNP planned orders? When you review the detail of the order in //RRP3, do you have both receipt and requirements elements?
Best Regards,
DB49
Let me try to be as clear as I can (apologies but my english is not upto mark)
The Business Requirement is for a Product (A) FG, has Component (B)Semi FG in its BOM. Also component (B)SFG has a BOM under it.
When we run multilevel heuristic SNP Planned orders gets created for Prod (A) and Component (B). The business wants to see these SNP planned orders as Planned orders in ECC.
So I ran a test in Dev where I changed the SNP Planned order to Planned order in RRP3. (screenshot attached using the button highlighted Yellow) So When I publish them to ECC in MD04 for prod A, I can see them as Planned order which is fine.
Now the same when I am trying to do for component (B) rather than changing into Planned orders they change to purchase Reqs. (please see screen shot). Both of them have procurement type as "X"
All I want is component B, to be published to ECC as planned order.
Many Thanks and I am glad that you are answering my queries, as I have been following you for long on scn community.
Regards,
Shaikh
S,
Your English is OK. It is much better than my command of any other language, since I only speak English, and I am envious of people like you, who have worked to master more than one language.
Planned orders for components are published to ECC in exactly the same way as they are published for the parent materials.
So, for the components, you need to have a valid production version in ECC, and this should be CIFd to SCM as a PPM or PDS. Your SNP planned order in APO for the components should look similar to the planned orders for the parent materials (have both a receipt element and a requirements element). The Product Masters of the components of the BOM for the B material should also exist in SCM.
Best Regards,
DB49
Many thanks.
Just one more thing.
If I want my Finished Good "A", SNP Planned Order to be changed in ECC to Process order (which is happening right now) but the Semi Finished Good "B" SNP Planned Order to be changed to "Planned Order" is it possible in standard or do we have to do any CIF customisation. Please note Semi Finished Good "B" also got a BOM and requirement is to have Planned order in ECC so that it can be changed to manufacturing order or purchase order depending on the requirement/situation.
Regards
S,
I have never seen an SNP Planned order in SCM integrated to ECC as a Process Order except through use of an enhancement. The only standard integration I am aware of is for an SNP Planned order to be integrated as an ECC Planned order.
Typically Process orders are created later in the planning cycle; by converting a planned order to a Process order.
So, to answer your question, the standard integration for SNP Planned order (either material A or B) is an ECC Planned order. No special configuration required.
Once the planned orders have been created in ECC, if you wish for the ECC planned orders to be converted to Process orders instead of Production orders, then that configuration/master data lies in ECC PP.
Best Regards,
DB49
OK. If the standard configuration for SNP Planned order is ECC Planned Order. Where can I see them in ECC?
I cant see the ECC Planned order against SNP Planned order in MD04.
Can you please share screen shot?
In our case when we change the SNP planned to PPDS and publish them it converts them in Production order for Material A (finish good) and process order for Material B (Semi finish).
I cant see the SNP Planned order as ECC Planned order in MD04.
Kindly guide as really confused!
S,
If the standard configuration for SNP Planned order is ECC Planned Order. Where can I see them in ECC?
MD04
Can you please share screen shot?
Not much to share. It is exactly the same as a Planned order created via any other means.
In our case when we change the SNP planned to PPDS and publish them it converts them in Production order for Material A (finish good) and process order for Material B (Semi finish).
As I said earlier, I have never seen STANDARD CIF create a process order.
In your example, assuming standard CIF and assuming no special procurement keys in ECC, you would normally integrate a PPDS planned order for A to an ECC Planned order for A, which would generate a dependent requirement in ECC for B. I don't know how you are getting the Process order.
With respect to SNP (which is the topic of this thread), in order to publish SNP orders to ECC, you would normally configure them so. What are your SNP configuration settings? In SCM, IMG > APO > Supply Chain Planning > Supply Network Planning > Basic Settings > Configure transfer to OLTP systems.
Best Regards,
DB49
Hi S s,
Please check the PPDS Global settings in customizing to see when to send the orders to ECC. You shiuld sselect value 'Always create transfer events' or some thing similar. This is the normal default setting. This in conjunction with 'Publication' and an Integration Model' for Planned orders should work.
you can confirm by creating a planned order and save it in APO. On refresh the planned order should have a number from ECC.
Thanks,
Subash
This is the setting I have. OK, I only talk about SNP planned order which is the topic of this thread. So from what you are saying, All i need to do is to change the setting In SCM, IMG > APO > Supply Chain Planning > Supply Network Planning > Basic Settings > Configure transfer to OLTP systems and create/activate integration model. After that SNP Planned order should be in ECC (MD04) as ECC Planned? I am doing it right now. Thanks for all the support, You really are a star!!
User | Count |
---|---|
12 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.