Dear all,

Please, maybe you can help me.

I have one question. In the Maintenance Plan Task List there is one component. The plan and the task list are generated for plant X. The material is from plant Y. The issue is that the field plant, in the task list, is greyed out. And, in the generated Work Order, the material is requested from the plant X, even if is needed from plant Y. How to set, to let the field from the task list component to be editable, so to be able to insert the correct plant there?

Thank you very much for your generous help.

Kind regards,

Sorin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Sorin,

Implement Note 441577 - Free material assignment in maintenance task list.

Regards