Skip to Content

Task List Component

Dear all,

Please, maybe you can help me.

I have one question. In the Maintenance Plan Task List there is one component. The plan and the task list are generated for plant X. The material is from plant Y. The issue is that the field plant, in the task list, is greyed out. And, in the generated Work Order, the material is requested from the plant X, even if is needed from plant Y. How to set, to let the field from the task list component to be editable, so to be able to insert the correct plant there?

Thank you very much for your generous help.

Kind regards,

Sorin

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 30, 2015 at 10:03 AM

    Hi Sorin,

    Implement Note 441577 - Free material assignment in maintenance task list.

    Regards

    Vivek

    Add comment
    10|10000 characters needed characters exceeded