Hello Experts,

I need your help to fix the priority issue.

Error During Mass Confirmation (COHV) of production order-

1)Confirmation can not be successfully saved.

2)Document XXX already entered for measuring time specified

Please find the attached Error screen shot.

Please can me directly on 9167088537

Sunil Patil

9167088537

cohv-mass-conf-error.png

P2003523347
Participant
0 Kudos

Hello Guys,

Could you Please help me to fix the issue.

Error During Mass Confirmation (COHV) of production order-

1)Confirmation can not be successfully saved.

2)Document XXX already entered for measuring time specified

Please find the attached Error screen shot.

Please can me directly on 9167088537

Sunil Patil

9167088537

cohv-mass-conf-error.png

cohv-mass-conf-error.png (548.7 kB)

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please, check the confirmation posting time and the system time ,

In COHV the future time input is accepted but for measuring document-reading will not accept the future time.

check your input date and time are different from the server time. If the time during the confirmation is ahead then the server time this error is occured.May be one of the reason . Please check and revert.

Regards,

Goutham

P2003523347
Participant
0 Kudos

Thanks Goutham,

I will check and let you know the same

Sunil Patil