How to find KO23 assigned value brakeup

Dear all,

I have Created Internal order and assign  budgect Rs.22400

I have not posted any document against order number. But

in Ko23 it is showing assigned value Rso Rs.21420.

In availability analysis it is

how to see  the documents and clear COSP table , in GL 6614082 no document.

thaking you

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Oct 27, 2015 at 10:25 AM

    Hi,

    There is a internal order commitment  report "S_ALR_87013019", which gives you detail analysis of all commitments. Double click each line item it will show you the PO assigned to it

    Hope it will clear you

    Regards,

    Inthiyaz shaik

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 27, 2015 at 10:57 AM

    Hi ,

    You have created a po and assigned internal order to it.

    Thanking you

    Vengaiah

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 27, 2015 at 12:29 PM

    Hi Soma,

    Please run report  S_ALR_87013019 to find out the relevant document no, for particular posting which has created assigned value either actual or commitment.

    This will give you all the details.

    And if you want to delete COSP records proceed as -

    1. RKACSHOW : Enter order to find out OBJECT NO.

    2. Run report  RKPLNC27 (refer to note 549760  ) to delete zero records in COSP (with parameters : object number, fiscal year, version)

    Please keep in mind it will delete the entries in COSP which has zero values.

    Thanks & Regards

    Pooja Gaur

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 28, 2015 at 01:54 AM

    Hello Soma,

    It should be a commitment value posted from purchase order or purchase requistion.

    You can find the details with report S_ALR_87013019.

    Best regards,

    Jason

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 28, 2015 at 07:49 AM

    Hi,

    Allotted/Commitment item/value:: PR value not which is assigned to PO,PO value which is not preceded by PR.

    Actual : posting to primery cost element(MIRO etc),including JV(FB60 entry).& Statistical  cost element at the time of MIGO

    Budget is being posted in ko22

    Availability control will act on  Budget > Actual +{(commitment - coresponding actual of the commitment) )

    Check detail in S_ALR_87013019



    ko23.png (47.3 kB)