POWL_QUERY - Status Overview

Hi,

On status overview page of PMP iView, I have a requirement where start date should be start date of current calendar year and end date should be fixed date i.e. '31.12.9999'.

If I don't use the POWL Query, the system defaults the dates to start and end dates of current calendar year. If I use POWL Query, then fixed dates are populated.

Can anyone please help to know how to set only start date as dynamic and end date as fixed.

Thanks,

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 27, 2015 at 06:12 PM

    Go to SAP ECC - Tcode POWL_QUERY >OSA_ESS_STATUS_OVERVIEW/OSA_MSS_STATUS_OVERVIEW > Quer Parameters https://scn.sap.com/thread/2113830

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Siddharth Rajora

      Hi Siddharth,

      I couldn't see the default dates now on Status Overview. I have edited the Query Parameters and the values appeared correctly on ESS.

      SAP ECC - Tcode POWL_QUERY >OSA_ESS_STATUS_OVERVIEW/OSA_MSS_STATUS_OVERVIEW > Quer Parameters


      Then I have removed the values from Query Parameters and I see the blank dates on Status overview. The default values(Start Date and End Date of Current Calendar Year) are not populated.