Hi,

We are create a BOM and done production in SAP B1

               Product.(Parent)             PC001       1 Nos

              Components                     Comp1      1 Nos

                                                      Comp2      1 Nos

                                                      Comp3      1 Nos

We want to split (disassemble ) the product (parent item) in SAP. please suggest the suitable solution

 

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Oct 27, 2015 at 07:21 AM

    Hi,

       I think  you posted in wrong space. Please post in  appropriate  space.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 29, 2015 at 03:49 AM

    Hi,

    SAP B1:

    In your production order screen you can find a field called 'Order Type" on your right corner with a drop-down list option as below:

    1. Production Order

    2. Dis-assembly

    3. so on...

    Order For a normal process like assembly,machining etc., will have this field as 'Production Order". Since you want to dis-assembly select Dis-Assembly option to this field and header material as PC001.

    Remaining things are as usual.

    While taking Goods Movement will be as below:

    1. During GI Parent Material PC001 will be consumed to make this Order.

    2. During GR Components will be returned to Store.

    Pls check, if found ok pls reward points.

    Thanks With Regards,

    Dinesh Kumar V.