Shift Delivery Date after PO Approval

Hi all,

I need to shift delivery date after PO last approval. Let me explain why;

PO created at 27.10.2015

Delivery Date is 30.10.2015

PO Approved at 30.10.2015 and printout sent to the vendor. Vendor delivered goods at 31.10.2015 which means after 1 day when he got the printout.

But if we look from PO side, vendor seems 1 day late. This cause problems in vendor evaluation.

Does anyone has suggestion on this?

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 27, 2015 at 12:40 PM

    Let's assume you have created PO at 30.09.2015 and the delivery date was 10.10.2015.

    The PO approved at 05.10.2015 so as per your requirement delivery date should shift to 15.10.2015?

    If I understood correctly you can do this using ME_PROCESS_PO_CUST

    with reference to

    EKKO-AEDAT

    and

    CDHDR UDATE field with relevant CDPOS document where FRGKE field has value "O".

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 27, 2015 at 06:22 PM

    The time needed for PO approval is to be included in the purchasing processing time which is defined per purchasing organisation in customizing.

    If you have not done that then it is better to do this so that planning can consider those extras days and would have suggested a later delivery date from the very beginning.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 27, 2015 at 04:40 AM

    Hello Sefa ,

    you have to use the fields Planned delivery time and Gr processing time for calcualting the exact delivery date.

    in material master you can give the planned delivery time as 1 day. then system should calculate the date according to it.

    thanks

    Kunal

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 27, 2015 at 04:49 AM

    Hi,

    What exactly you need as per my observation that after approval delivery date should be changed i.e. if approval is of 30th Oct then delivery date should be 31st Oct. If this is the requirement then how system know that how much days you want to shift? Please elaborate.

    Regards

    Ajay

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 28, 2015 at 07:44 PM

    Also I would not recommend the change in the PO once it is approved. You need to consider this time in your planning .. How many POs are that are get effected because of this ??... if you see vendor evaluation is effected.. you can award him some manual points so that he can come at par.. If I am at your place I will not try this option but look a way to bring the vendor points at par as these cases are not as frequent as it look to you ..

    But you have take in consideration your PR processing time and keep on sending PO approval reminders till the time it release .. PO that get delayed and not approved..business can make changes in delivery dates..