Skip to Content
avatar image
Former Member

CJ30 (Change Budget) & CJ32 (Release Budget)

Hi Experts,

I have one logical query regarding the above mentioned transactions please.

Logically, if i create budget through CJ30 for any particular Project or WBS and after this, if i try to execute any transaction with reference to that Project or WBS then system should restrict/prompt me that i have not released it therefore i am not able to proceed further with the same project/wbs.

Once the budget gets released, system should allows us to proceed within the specified limit and that is what control is.

Now, in my scenario, if i create budget on any Project/WBS through CJ30 and try to execute any transaction with the same Project/WBS then system allows me to do so which is wrong and therefore we are looking for any control.

Please guide.

Regards,

Zain Bashir

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 27, 2015 at 12:07 PM

    Hi Zain,

    System activates the AVAC when budget is released before status remains BUDG only. You are looking for control before budget gets released then user status must help. You can maintain the user status at WBS level in such a way :

    1- CRTD- Created.

    2- BUDG- Budgeting done.

    3- BREL- Budget released.

    Once you select the option 2- budgeting done then system will not allow you to post anything actual.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 27, 2015 at 05:56 AM

    Hi Zain,

    Just a clarification. Transaction you mentioned is the Transaction codes (CJ20N, CN22 etc) or posting like planning commitment, PR, PO etc.

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 27, 2015 at 08:57 AM

    Hi,

    You can activate availability control on release budget so that you have control on released budget only.

    The value you entered in CJ30 is the original budget and the budget you release is through CJ32. You can also release only some % (for example 90%) of original budget. So you have two level controls

    1. While releasing the budget

    2. Availability control on released budget

    Hope this helps

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 27, 2015 at 09:06 AM

    Hi Zain,

    You can review the above article: Prevent release of WBS-element before Budgeting.

    The latest version touches on availability control based on Released budget scenario.

    Regards,

    Paulo

    Add comment
    10|10000 characters needed characters exceeded