on 10-26-2015 1:04 PM
kindly suggest me on below scenario.
Releasing the forecast successfully from DP to SNP, my selection is depot (400, 450, 900 & 950) product is (1031) & date is 01.11.2015 to 15.11.2015. Total 15 days and these forecast is releasing to production plant 1001, but results are showing at plant level as example shown in below
depot plant product date quantity
400 1001 1031 01.11.2015 100
450 1001 1031 01.11.2015 50
900 1001 1031 01.11.2015 200
950 1001 1031 01.11.2015 100
400 1001 1031 02.11.2015 100
450 1001 1031 02.11.2015 50
900 1001 1031 02.11.2015 200
950 1001 1031 02.11.2015 100
400 1001 1031 15.11.2015 100
450 1001 1031 15.11.2015 50
900 1001 1031 15.11.2015 200
950 1001 1031 15.11.2015 100
But my problem is: I want to sum all the depots demand of same day and update at plant 1001 for the given product.
it means as shown below:
at plant 1001, demand is 450 for product 1031 on date 01.11.2015
at plant 1001, demand is 450 for product 1031 on date 02.11.2015
at plant 1001, demand is 450 for product 1031 on date 15.01.2015
Kindly suggest me in which enhancement i will implement this changes.
Thanks
Jamal.
Hi Amol
Thanks for reply.
If i go with NOTE,
Is it sum the forecast of all depot of the same day and release one order to SNP?
Can i see that sum value with one forecast order from RRP3?
My requirement is only one forecast order per one day would show in rrp3.
appreciate if you reply with example.
Thanks
Jamal.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No Jamal
As you have 3 different Depots, it would create 3 orders for each depo and put on Plant.
I think in your case look for option 3 which has mentioned above i.e. you can also bring all the demand planning data into APO BW. With transformation you can assign the plant to all the respective depots. With using appropriate aggregates and T-code /SAPAPO/REL_TO_SNP - Release from InfoProvider to Supply Network Planning, you can release the FCST to SNP.
Thanks
Amol
Hello Amol,
I understood your valuable suggestion and your suggestion is helpful answer.
But here decision has made by DP business team and asking us to do this enhancement through /sapapo/mc90.
please suggest me how will make it using /sapapo/mc90.
I will go with option 3 if there is any difficulty using /sapapo/mc90.
Thanks
Jamal.
Hi Jamal
Please refer the below OSS note which will provide you all the details.
Ideally from DP -->SNP you release the FCST on same plant i.e. in your case Depots and execute the SNP to transfer the demand at plant. With this approach all the dependent demand from Depots will get aggregated and transferred to plant. If we same lead times, then you can achieve the above results.
Please also check the /SAPAPO/MC7A - Location Split , functionality if it works for you. You require to play little bit to see if it´s fulfill your requirement.
Lastly you can also bring all the demand planning data into APO BW. With transformation you can assign the plant to all the respective depots. With using appropriate aggregates and T-code /SAPAPO/REL_TO_SNP - Release from InfoProvider to Supply Network Planning, you can release the FCST to SNP.
Please let us know if the above information helps you. In case if this answers all your question, please close the question with appropriate feedback.
Thanks and Regards
Amol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.