kindly suggest me on below scenario.

Releasing the forecast successfully from DP to SNP, my selection is depot (400, 450, 900 & 950) product is (1031) & date is 01.11.2015 to 15.11.2015. Total 15 days and these forecast is releasing to production plant 1001, but results are showing at plant level as example shown in below

depot     plant      product     date               quantity

400        1001       1031          01.11.2015       100

450        1001       1031          01.11.2015         50

900        1001       1031          01.11.2015       200

950        1001       1031          01.11.2015       100


400        1001       1031          02.11.2015       100

450        1001       1031          02.11.2015         50

900        1001       1031          02.11.2015       200

950        1001       1031          02.11.2015       100


400        1001       1031          15.11.2015       100

450        1001       1031          15.11.2015         50

900        1001       1031          15.11.2015       200

950        1001       1031          15.11.2015       100


But my problem is: I want to sum all the depots demand of same day and update at plant 1001 for the given product.

it means as shown below:

         at plant 1001, demand is 450 for product 1031 on date 01.11.2015

         at plant 1001, demand is 450 for product 1031 on date 02.11.2015

         at plant 1001, demand is 450 for product 1031 on date 15.01.2015


Kindly suggest me in which enhancement i will implement this changes.



Thanks

Jamal.


Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Amol

Thanks for reply.

If i go with NOTE,

Is it sum the forecast of all depot of the same day and release one order to SNP?

Can i see that sum value with one forecast order from RRP3?

My requirement is only one forecast order per one day would show in rrp3.

appreciate if you reply with example.

Thanks

Jamal.

Former Member
0 Kudos

No Jamal

As you have 3 different Depots, it would create 3 orders for each depo and put on Plant.

I think in your case look for option 3 which has mentioned above i.e. you can also bring all the demand planning data into APO BW. With transformation you can assign the plant to all the respective depots. With using appropriate aggregates and T-code /SAPAPO/REL_TO_SNP - Release from InfoProvider to Supply Network Planning, you can release the FCST to SNP.

Thanks

Amol

Former Member
0 Kudos

Hello Amol,

I understood your valuable suggestion and your suggestion is helpful answer.

But here decision has made by DP business team and asking us to do this enhancement through /sapapo/mc90.

please suggest me how will make it using /sapapo/mc90.

I will go with option 3 if there is any difficulty using /sapapo/mc90.

Thanks

Jamal.

Former Member
0 Kudos

Hi Jamal

Please try the BADI /SAPAPO/SDP_RELDATA. I am sure you can do data manipulation with in the BADI. You can change the location from Depot -->Plant and release the FCST to SNP using /sapapo/mc90.

Please close the questions using appropriate actions from your side.

Thanks

Amol

Former Member
0 Kudos

Hi Amol,

Thanks for your suggestions.

Thanks & Regards,

Jamal.

Former Member
0 Kudos

Hi Jamal

Please refer the below OSS note which will provide you all the details.

Note 403050 - Consulting note: Release from DP to SNP

Ideally from DP -->SNP you release the FCST on same plant i.e. in your case Depots and execute the SNP to transfer the demand at plant. With this approach all the dependent demand from Depots will get aggregated and transferred to plant. If we same lead times, then you can achieve the above results.

Please also check the /SAPAPO/MC7A - Location Split , functionality if it works for you.  You require to play little bit to see if it´s fulfill your requirement.

Lastly you can also bring all the demand planning data into APO BW. With transformation you can assign the plant to all the respective depots. With using appropriate aggregates and T-code /SAPAPO/REL_TO_SNP - Release from InfoProvider to Supply Network Planning, you can release the FCST to SNP.