Standard SAP report on WBS element status change

Hello people.

Today I read some discussions about the subject of my question. But I didn’t find the answer I'm looking for: is there some standard report where I can see the changes of a WBS element?

In the project profile I have this situation on Status Management:

  • Status profile for project definition: none. I can choose from more than 1.
  • Status profile for WBS element: none. I can choose from more than 1.
  • Change documents Indicator: selected.

I'm trying the CN60 transaction without success.

Does anybody know some standard report or have some suggestion? I need to see when e who changed the status.

Thanks a lot in advance for any help.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Best Answer
    Oct 26, 2015 at 01:40 PM

    Hello Ricardo,

    a simple query on table JCDS with internal object number for WBS element (like PRXXX) .

    With a simple query with table join PRPS ->JCDS->JEST you can obtain a nice report for the modifications.

    Best regards.

    Roberto

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 26, 2015 at 01:16 PM

    Hi Ricardo Mano,

    We can view list of  WBS status changes by user id, action and timestamp. click on the i button (in blue color) in WBS screen and hit on Extras (on top left of menu bar) change documents -- ALL and All changes.

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 26, 2015 at 01:27 PM

    Hi Ricardo,

    Simple solution would be to create a sqvi report using JEST table and pass the OBJNR you will get the changes to the status.

    Thanking you

    Vengaiah

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 26, 2015 at 03:21 PM

    Hi

    You can see the audit trail of status change for wbs element from it's detail screen itself

    Click on the info tab next to status field and then you get all status information in Display status page. In the same status detail page go to menu: Extras -> change documents -> all then again click on all changes

    this provides complete information about the changes to all statuses. Hope this helps

    BR/ Raghu

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 26, 2015 at 04:10 PM

    Ola Ricardo,

    Note that in the project profile you have two flags for Change documents, one is generic, and another is specific for Status Management.  You need the second one to be active.

    Cump,

    Paulo