Hello

I want to delete some planner groups in Production system.Before i want to know the routing materials assigned with the planner groups to be deleted .So that i will modify the planner groups assignement with live materials,.Thank you in advance

venkat 

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 26, 2015 at 10:09 AM

    Hello

    You can use CA80,in the combination of Workcenter and Planner group to get the Routing list.

    You can use CA51 to idebtify the list routing.

    Regards,

    Velmurugan S

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 26, 2015 at 10:14 AM

    Hello,

    Planner group for a routing is stored in table PLKO, field VAGRP.

    Assignement of routing to material is stored in table MAPL.