Clarify the Transport Request?

Hi Experts,

        I'm new to SAP, When i tried  to release the transport request from development to quality,it have two request by default. May i know what is the purpose of that two request ?

Could you please clarify the above mentioned two request.

Regards,

Dinesh Kumar

Request.JPG (9.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Oct 26, 2015 at 01:54 PM

    Hi Dinesh,

    based on our screenshot, you are having 1 transport order.

    IDSK900964 => Transport request (top level)

    IDSK900965 => Task

    Objects that are created//changed/deleted, can be recorded into a SAP Transport request(s).

    Once object(s) has/have been changed, it/they gets/getting object lock(s). This is captured into a task of a transport request. The locks remaining until the task/transport request gets released.

    By that concept, SAP "organizes" it changes, for example:

    You create a new table, its field, views, etc.

    This change is recorded into a transport order/task under your SAP user ID.

    Now it could be the case, you need to speed up the design part.

    A colleague would now create the views. You would assign the colleague a new task.

    Once the work has been finished, you release the transport, to be able to release it to its target system, or provide it to other SAP Systems.

    Working with the Transport Organizer - Software Logistics - SAP Library

    Best regards

    Carlos