Hello Sap PPM,
We have existing Portfolio Initiatives with decision points. We want to reconfigure and delete few existing decision points in configuration.
How can we correct exiting data with new decision points?
-Diana
Hello Diana
When using the 'change process' functionality the system allows for the changing from one Initiative/Item type to another. During this step the user can choose to delete or rename existing decision points. You can possibly look into this code and create a Z*program to do this on mass (unless you are ok to do this manually for each Initiative).
Take note of the following :
1. You will have to configure a new Initiative type when switching the lifecycle (but in theory you will be able to switch back to the old Type if needed),
2. Any existing Decision Point link to phases are lost (i.e. do you have associated cProject phases? If so the links are broken for those decision points that you delete)
Regards
C
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
7 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.