Upgrade Pre-Requisite

Hi,

We have a scenario where our ECC landscape is going under an upgrade.

In this scenario, do we need to Stop the replication Jobs from SLT side.

Since the ECC upgrade is going on a shadow instance, we have a plan to stop the SLT replication (master Job) just before the down-time starts for ECC. For other Pre-processing steps for ECC upgrade, can SLT master jobs  can be switched on ?

Thanks

Mrityunjay

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Oct 26, 2015 at 01:43 AM

    Hi Mrityunjay,

    Yes, Replication can be on while upgrade pre-processing is running.

    Stop the replication before downtime starts and it can be started after the upgrade.

    Thanks

    Dass