HI

Before I enter old data in stability plan. But form last week i am facing problem

Example I create one notification which is starting 26.01.2014

and Planning as 3M, 6M, 9M, 12M , 18M and 24M

But when i make through IP 10 it's showing only one plan that 24M

I tried several way but not result could please help  any one how to resolve the issue.

Thanks a lot.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 25, 2015 at 11:53 AM

    Hello Abdul,

    This is because all other schedules passed away since start date 21.01.2014. Only 24M schedule is in future (26.01.2016). So it is being called. If you want see all these from today in future dates, then use Restart button at the top and give today's start date.