MRP RUN after chane of plan figure automically

Dear Expert ,

Our organization is a nature of process industry and production plan are changing frequently , as result every time we need modify PIR and then we have perform MRP RUN through t-code MD02 . This is very tedious to end user .

Hence we want to develop a tool , after  changes of plan figure , at the end day , from PBIM and PBED combination,  MRP RUN will run will perform atomically.

Please help me how to do the configuration .

Regards,

Amit Biswas  

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Oct 24, 2015 at 03:31 PM

    Hi, use tr. MDBT to create a periodically background job.

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 25, 2015 at 06:34 PM

    There is no configuration to automatically trigger the MRP run after a PIR change.

    A PIR change is considered a MRP relevant change, therefore, the planning file is updated and this material will be included on the next MRP run. As already mentioned by michael, you should simply schedule a daily MRP run and your material will be planned after the planning run.


    Regards

    Caetano