Adjusted Production Receipts

Former Member
0 Kudos

Some adjustments were made in Production Receipts -  but now I would like to reset and let SPO run again.

What is the best procedure to do that?

Thanks, Renata

Accepted Solutions (1)

Accepted Solutions (1)

pramod_mane2
Participant
0 Kudos

Hello Renata,

You can create an SCM Operator with additional following parameter

RESET_ADJUSTED_KEY_FIGURES set to YES.


This parameter resets all the Adjustments made.


Thanks

Pramod


Former Member
0 Kudos

Hello Pramod

Is there any documentation that can guide me to do this?

Thanks, Renata

pramod_mane2
Participant
0 Kudos

Hello Renata,

You can find documentation in section 10.8.1 (parameters of SCM operator) of the model configuration guide.

http://help.sap.com/download/ibp/ibp40_model_ref_en.pdf

Thanks

Pramod