Skip to Content
avatar image
Former Member

Half day leave calculation in CATS


Hello,

I have a scenerion where Total target hours as per work schedule is 8.25 hours daily.

And if employee apply for half day leave the total hour claculated by system is 4.13 hours.

Now if employee apply for Leave in one go for. eg. Morning and Afternoon then system calculates it correctly as 8.25.

But if he applies and create two records for the same day then system throws an error as 4.13 + 4.13 becomes 8.26 which is incorrect.

what could be the solution if we do not want to change the total Target hours from 8.25 to 8.26.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 23, 2015 at 01:14 PM

    What your expecting? when you record absence in CATS then the absence hoursĀ  is coming around 4.13 but it should be 4 hours? am i correct? if so, you can use 'daily work schdule varient for absence' V_550X_B.

    here you dont need to change your actual working time 8.25. but you can create a varient for 8 hrs and this will be called when your recording absence. so according to that varient when you record half day absence, it will be count 4 hrs.

    Add comment
    10|10000 characters needed characters exceeded