Quality stock not included in Planning

Hello all,

I have a stituation  where in  the  MD04, the net planning does not count in the Quality stock.

I earlier checked the OPJJ - under PP checking rule, where "Include Quality Insp stock" is ticked.

also in OPPQ - only the stock in transfer is ticked.

Could you please let me know if there is any settings else where, the stock moved to Quality stock is also taken as available during Net requriement planning. Thanks

Regards

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Oct 22, 2015 at 08:04 PM

    Hello

    OPJJ is the availability check customizing and it is not relevant to MRP.

    Generally, MRP considers the inspection lots as MRP elements instead of simply add the quality stock to the total stock. Do you see inspection lots on MD04?

    Regards

    Caetano Almeida

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Caetano Almeida

      Hello Caetano,

      My bad..i do see a Inspection lot created in md04, when stock is moved by 322 mvt, (as a inspection 08 is setup.)

      I suppose this is it. Will further enquire if this is the issue. Will reopen if not. Thanks

      Regards