GR on production order in restricted

Hi experts,

Do you know if it's possible to make a GR on production order in restricted-use, instead of quality inspection.

This, in order to facilitate stock movements while inspection is on ?

Inspection for HU is active, inspection type 04.

Thank you in advance.

Kind regards,

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Oct 22, 2015 at 03:48 PM

    Hi Giacco,

    Do you have Batch status management active ?

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 22, 2015 at 10:26 PM

    If batch status is activated you can set the default on all new batches to be automatically created as restricted.  This is a configuration setting.  I believe the menu item is something like "initial batch status" and is under the batch management config.  If you can't find it, let me know.

    Craig

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 23, 2015 at 07:41 AM

    Hi Craig,

    I guess I've found it but still, my batch is received in unrestricted use...


    pastedImage_0.png (15.8 kB)
    Add comment
    10|10000 characters needed characters exceeded

    • Yes.. I think you have it.  but your screen is different than mine because it looks like you have batch level at the plant level.  (if this is a new instance of SAP I highly recommend you consider using batch level at material or client level and not plant level.)

      I can't verify for sure because of the our settings but I believe that the last column is indicating if batch status is active or not and it appears it's not. (I don't have that last column in my configuration).  So first make sure the plant is activated for batch status management.  It's the config item just prior to the one you display above and it is logically called "Plants with batch status management".

      Once you are sure batch status is active for the plant.  Then you can set the initial status on for the various material types.

      Craig