Reduction of planned independent requirements goods receipt for a production order discrete production

Hi Gurus,

I have a fert that consumes a halb. I would like to put the RIP only HALB, and when making a goods receipt for a production order to consume the RIP of HALB. What strategy should I use?

I

Thaks for help me.

Best Regards.

Leandro

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Oct 21, 2015 at 11:29 AM

    Hello

    You can use the Gross Requirements Planning (11) for your requirement where reduction of planned independent requirements takes place during goods receipt for a production order (Dscrete), for a planned order (REM)

    Regards,

    Velmurugan S

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.