Reduction of planned independent requirements goods receipt for a production order discrete production

Hi Gurus,

I have a fert that consumes a halb. I would like to put the RIP only HALB, and when making a goods receipt for a production order to consume the RIP of HALB. What strategy should I use?

I

Thaks for help me.

Best Regards.

Leandro

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 21, 2015 at 11:29 AM

    Hello

    You can use the Gross Requirements Planning (11)  for your requirement where reduction of planned independent requirements takes place during goods receipt for a production order (Dscrete), for a planned order (REM)

    Regards,

    Velmurugan S