Plan cost inconsistency

Hello colleagues, I need some help from you.

When we plan costs in a network activity, the parent WBS element will also show those costs in a report(cost element, for example). My problem is that when I physically delete the network activity without first removing the planned costs, the costs will keep showing in the report for the WBS element. That is a big inconsistency, in my opinion, but SAP says that this is normal behavior.

Anyone knows how I can avoid this? My users want me to do write ABAP code to delete those planned costs from the WBS, but I do not want to go so far and would prefer an easier solution.

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 21, 2015 at 12:15 PM

    Hi Alex,

    Can you please cjen tcode.

    Thanking you

    Vengaiah

    Add comment
    10|10000 characters needed characters exceeded

    • Oi Alexandre,

      Just as idea you can schedule this correction program in background, even though not sure how often the described situation takes place and if you can get any smart selection criteria for this utility.

      You can also implement an enhancement that calls it automatically upon network saving when some NWA are marked for deletion.

      Regards,

      Paulo

  • avatar image
    Former Member
    Oct 21, 2015 at 01:17 PM

    Dear Alexandre,

    The best practice as mentioned by Vengaiah is simple. You Need to clear the costs before deletion or locking. It is in simple Terms, throwing away your old wallet with Money in it. But this Money Shows in your value lost but instead you Need to remove the Money and throw the wallet.

    😊

    Regards

    Vittal