except raw materials no activity shown at the time of cost estimate

we are in sale order based costing. when we create cost estimate system is not showing any activity type. it shows only the cost of raw materials. activities are assigned in cost component structure and manual planning kp26 is done correctly. activities are also assigned in work center in costing tab.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 22, 2015 at 06:44 AM

    Thanks a lot all of you for your cooperation.

    issue resolved. problem was on pp side. routing shows activity correctly but not capturing the figures, anyways, the pp guy resolved it.

    points assigned to everyone for your cooperation.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 21, 2015 at 07:29 AM

    Hi

    Check your valuation variant in costing variant whether proper routing id is selected

    kamal

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi

      Surprisingly it is not showing any warning msg also. However take the all screen shots of costing data, qty structure and valuation..if we could get some hints..

      It is clear that some link is missing for activity...

      kamal