Interface between HR and PP

Dear Expert

Our company want to record the employee's salary to sepecific process order. I only know we can record the personel data when doing confirmation by COR6N. But i don't know how to achieve this object. Are there some reference document to teach me? Or anyone can tell me the specific procedure?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Oct 21, 2015 at 05:35 AM

    Hi Mars,

    This is purely business requirement coming from customer. You have to translate into SAP objects to meet it.

    There are 6 Activity types in Routing ... These represent the way you can charge various cost(Other than Material cost) to Process order Operation. Typically you will have MAchine & LaborĀ  activity types & they represent the cost of using machine( Depericiation that occurs due to machine usage) and Cost of Labor attending the machine while it was processing operation step. If you have 2 employee attending machine , your labor activity type time need to be double of machine activity type.

    Labor activity type can be assigned different Salary rates based on grade of employee operating machine... You can define in CO module using KP26 Traxn.

    Hope it helps,

    Jatin

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Jatin

      I know your mean. But my qeustion is if these 2 employee's salary are different, how to deal with it?

  • Oct 21, 2015 at 05:47 AM

    hi Mars,

    you can assign employee to particular work center also you can see the capacity based on the present/absent of worker

    hope this helps,

    http://scn.sap.com/thread/3457383

    regards,

    Solomon