Hello friends,

I am facing problem in changing "Valid To" date of BOM, i have created ECN for that & did lots search and try but doesn't works.

Which date I should put in "Date - Lower limit" and "Date- Upper limit " field in CC02

Will you please help..

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Oct 21, 2015 at 05:51 AM

    Hello,

    Just create new change number with valid from date as ex 10/22/2015.

    Now go to CS02 enter the this change number and delete the component which valid date you want to change or you can add new component.

    So that valid to date from component will be 10/22/2015. you can check this in CS03.

    Best Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Brahmankar sir,

      I followed process suggested by you the issue is resolved.

      Thanks a lot,

      Sushil.

  • Oct 20, 2015 at 03:55 PM

    Hi Sushil,

    Can you please provide screenshot of CC02 with lower & upper date limits you are referrring to ?

    Regards,

    Rohit

    Add comment
    10|10000 characters needed characters exceeded