MRP Generating Requisition if date does not meet the demand date

adeel_sarwar
Contributor
0 Kudos

Hi

I have an example where I have a demand order and supply order. If the supply date is before the demand requirement date there is no problem. MRP runs and does not create a requisition or planned order which is what I expect. See screenshot below after I have ran MRP.

Now if I change the supply date to finish after 11.11.2015 in the above example e.g. 31.12.2015 and run MRP again it creates me a requisition or planned order depending on the MRP settings.

I was hoping to see an exception message on the supply order to ask to pull it forward in order to hit the demand date as opposed to making or buying a new one.

I also validated my rescheduling configuration via OMDW and my rescheduling horizon is set at 365 days. I went through note 1745312

Regards

Adeel

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Adeel

Dependent reservations are not included on the rescheduling check by default.

Try to implement the modification note 203151 and test again.

BR
Caetano

adeel_sarwar
Contributor
0 Kudos

Thanks Caetano, that worked.