Complex SLT Configuration in HANA

Former Member
0 Kudos

Hi Experts,

We got a project to implement SLT for our HANA SPS09, but issue is We got 3 Source systems(3 ECC systems) to be connected with standalone SLT from there it has to connect with HANA system.

But question is can we have single standalone SLT for 3 dev, 3 Qua, & 3 Prd Source systems to connect with hana systems.

Please suggest either we have to go with separate standalone for all 3 sources or single is also possible.


If it is possible can someone please explain me the procedure.

I would appreciate if someone provide some documents for it.

Note: All three ECC systems are on different EHP's.

After configuration I have doubt, If we have same tables in all 3 sources will they overlap in target system or it will store on different schemas.

Pleas spill the beans on it.

Thank you

Regards,

Naveen.k.sura

+918008194458

Accepted Solutions (0)

Answers (2)

Answers (2)

lucas_oliveira
Advisor
Advisor
0 Kudos

hi all,

I'm moving this to the appropriate space.

BRs,

Lucas de Oliveira (moderator)

dmitry_kuznetsov1
Active Participant
0 Kudos

Hi Naveen,

I wil lstart from the last point: according to Section 3 in Admin Guide, prerequisites for SLT on ECC side are:

  1. NW 7.02
  2. SAP Kernel 7.20EXT

I have not heard of any technical restriction connecting 9 SAP systems to 3 HANA instances (if I got it right), but:

  • It will need to be quite a powerful system to handle the data volumes / jobs running in parallel / other dependencies
  • You will not be able to transport the config = all settings will need to be done manually for all 3 landscapes
  • you can do N:1 setup (e.g. 3 SAP DEV systems to 1 HANA schema), but it is a decision you will need to make if you want it this way. Table contents might be overwriting each other, think Currencies, Material MD, etc.)

Hope this does answer your question?