Hi.. Experts ,
please suggest the way for AMC Maintenance or Equipment :-
i'm following the below :-
1. Create Service Master.
2. Create Outline Agreement
3. Create General Maintenance Task list
4. Create Maintenance Plan
5. Schedule Maintenance Plan
6. Release Maintenance Order
7. Create Purchase Order against the Purchase Requisition
8. Create Service Entry sheet against the Purchase Order
9. Perform TECO for the Maintenance Order
sd
if i have more then one equipment then which process i need to follow to cater the requirement.
suggest the better way for more equipment AMC at one time.
Hello Lokesh,
You have lot many open threads. Please review and close wherever relevant.
Regards
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lokesh,
You mentioned correct process.Same way you can assign more equipments in your Outline Agreement with different line items eg.1000,2000 etc.Rest process same.
Regards
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.