Hi dear experts,

For all good receipts performed in division, there is a light inspection done to check if quantity ordered corresponds to quantity received. It means, we check if we have the right quantity, the exact color, not damaged, and so on.

we'd like to have a reference inspection plan that could be assigned to all materials by one transaction. ANd for any new product coming from the PLM (engineering and product lifecyce mgt) we'll assign this reference inspection plan.

Thanks in advance for your help

Best regards

Accepted Solutions (1)

Accepted Solutions (1)

busyaban7
Active Contributor
0 Kudos

Hi Patrick,

I believe you should have tried QP02 to assign materials to inspection plan, using the Material Assignment tab. Is that not helping you? Are you experiencing any error messages?

Thanks,

Arijit

Former Member
0 Kudos

Hi Arijit,

Thanks for your answer.

I tried this solution and it's fine. However let's say we have a reference inspection plan X1 and product A is assigned to it.

After new product B creation, I have to go in QP02 for product A, using the Material assignment tab before assingning the product B.

Can we have a more direct way to do this ? I mean by selecting the inspection plan and assign the product directly

Best regards

anand_rao3
Active Contributor
0 Kudos

Although I didn't follow you correctly, I guess you have the difficultly in putting material code as input in QP02. You can input the group number instead of material A when you go to QP02. Would that minimize the efforts?

Anand

Former Member
0 Kudos

Hi

Thanks all for the answers

I close the thread

Answers (0)