Skip to Content

MF50 Planned order VS MRP type X0

Hi Friends,

In our Project, APO is planning all materials and sending Planned orders/Production orders (Since SNP/PPDS are there).

So one user complaining that a Planned order basic dates goes wrong.

Query is whether MF50 Planning table can create Planned orders in spite of MRP type X0??

If so, Materials is having any Floats (SMK is 000), In-house production time is zero, bu system is taking Start date and end date gap is 3 days.

Please let me know whether planning table MF50 will it consider Lead time scheduling (Routing data).

I have not worked on MF50 much, please let me know.

thanks

Nag

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Oct 20, 2015 at 06:45 AM

    Hello,

    Please check the setting of OSP1 Start: current date+

    The basic dates of the planned order are calculated based on the production end date specified in Transaction MF50.

                  The basic dates are determined backwards with regard to the in-house production time of the material from the material master

    Please refer OSS note 397566 - R/3->APO: Date shift with planned order

    Best Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Friends

      I got the solution, as in the routing " Capacity view of Operation there was " No overlapping "  check box was set hence system system was taking start date as previous day.

      We removed that check box its giving dates as required.

      Thanks

      Murali