Hi sap guru,

We have created value contract with item category W, only provided material group in each line item.

as per requirement, scheduling aggrement creation will be refer against contract.

value of scheculing aggrement is more than target value of contract, but system is not showing any error message of value exceed.

We have checked in ME38 also, after maintaining schedule line, system is not throwing error message of value exceed.

But same is working at ME21N, on value exceed system, will throw error message of  contract value exceeded.

Kindly provide guidance in standard, cant we use value check in scheduling agrrement against value contract.

With Regards,

Nani

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 20, 2015 at 04:54 AM

    Hi,

    When the scheduling agreement is created the system does not recognize the target value until the delivery schedule is created.This is why the schedule can be created without any error.

    In Purchase orders you will get an error if the total PO value is greater than the value contract.

    Regards

    Ajay