SAP B1 9.1 PL09 Receipt from Production

benchristoffels
Participant
0 Kudos

We have updated to 9.1 PL09 over the weekend and noticed  a big change in the receipt from production.  There is no longer the ability for us to change the price list anymore.  We would usually change it from "Last Purchase Price" to another internal price list.

Is this correct or am I missing something?

Accepted Solutions (1)

Accepted Solutions (1)

frank_wang6
Active Contributor
0 Kudos

If you are using Moving Avg, the system will take the moving avg cost of components, and add them up as your final product cost for this transaction. It doesn't care the price list.

Frank

benchristoffels
Participant
0 Kudos

Thanks Frank.  We are using standard cost.  It is pulling in the warehouse cost, where before it was allowing us to choose a pricelist.

frank_wang6
Active Contributor
0 Kudos

if you are using standard cost, same thing happened. The cost will be from your standard cost. Even if u could select a price list, it will NOT make any difference. This is how standard cost works.

What I am saying here is no matter you can choose a price list here or not, it will post no difference, since the product process is not related to the price list at all.

Frank

benchristoffels
Participant
0 Kudos

Undertsood, but I am not sure why I believed it mattered before.  Thanks for the clarification.