How to fetch the Work Schedule rule from IT2003 in PCR's

venkat_polisetty
Active Contributor
0 Kudos

Dear Experts,

I have a requirement to fetch the WORK SCHEDULE RULE from IT2003 in PCR's.

Kindly help me out.

Regards,

Venkat Polisetty

Accepted Solutions (1)

Accepted Solutions (1)

sikindar_a
Active Contributor
0 Kudos

Use

VARSTSUBST

venkat_polisetty
Active Contributor
0 Kudos

Hi Sikinder,

Thanks for the update !!!

After fetching the subtype of Substitution (IT2003), how can call work schedule rule from IT2003.

Kindly help me out.

Regards,

Venkat Polisetty

venkateshorusu
Active Contributor
0 Kudos

Use below two operations VARSTSUBST, OUTWPSHIFT to read work schedule rule.

Before that check system over writes the work schedule rule and updates PSP when we maintain IT2003, It depends on the schema settings.

Depends on the requirement you can play around.

Regards

Venkatesh

Answers (1)

Answers (1)

Sanky
Active Contributor
0 Kudos

Hi Venkat,

When you will use the IT2003 that time I think it's been updated PSP table through the function P2011 so you can use the operation OUTWPSHIFT for this.

Check once and let me know.

Regards,

Sankarsan

Sanky
Active Contributor
0 Kudos

Hi Venkat,

If your query is answered then close the thread with correct answer marking.