Do I need to take any precautions to activate the BW objects

Former Member
0 Kudos

Dear Experts,

I need to activate all DSOs,Inco Cubes, Multi Providers, Info objects, Transformations, Data sources, DTPs and Infopackages by running the respective programmes in Production System.

As it is production system, can you suggest me, do I need to take any precautions to activate all the above objects by running the respective programmes..

Thanks,

Suresh.

Accepted Solutions (1)

Accepted Solutions (1)

former_member183519
Contributor
0 Kudos

Hello ,

In activation always go from top to bottom.

ex .  Multiprovider to DSO with their respective Trans's & DTP's.

Regards,

Hitesh

Former Member
0 Kudos

Hi Jugal,

Yes it is for the up gradation and activated in the quality.

How to put all the inactive objects with the before image. Can you guide me step by step.

Thanks,

Suresh.

Former Member
0 Kudos

Hi,

If this step is already done in quality, you can follow the same drill (steps) as done before.

Please check if you have to activate all the objects ? or only the objects became in-active in comparison to before image ?

Thanks

-J

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Suresh,

I am assuming the activation are required for some sort  migration / upgrade scenario ?. If that is the case I assume you have inventory of all the objects before image. 

Have you already simulated this step in your acceptance / quality environment as well ?

If you are activating the DSO , cubes etc. Please do not forget to activate the related transformations and DTP.

Please do check all the in-active objects with the before image.

Thanks.