Hello,


Can you explain me what are the meanings of Planned Qty and Old Qty in MD73 report - Output list 3?

What is the relationship with the dates listed there?


Thank you

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Oct 19, 2015 at 08:45 AM

    Hello Andreea,

    Planned and Old quantity in MD73 shows the history of planned independent requirement (PIR). Planned quantity shows the total PIRs created for a particular material during a time period. Once these requirements are deleted from system (either manually or by a background job) system updates the Old quantity field. In total it shows you how much was created in past and how much got deleted. The date / time specifies the actual date / time of event.

    For example, if I create PIR for a particular material on 18.11.2015 at 11:00 AM and delete them on 19.11.2015 at 4:00 PM then there will be 2 entries in MD74. First with planned quantity and another with old quantity along with exact quantity and time stamp.

    Regards,

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 19, 2015 at 01:36 PM

    Hello

       Planned quantity is current  quantity of PIR  after reduction

       Old quantity is quantity of PIR before reduction,we can say it as original quantity entered in MD61.

    Regards,

    Velmurugan S