Material Price updation in other plant

Former Member
0 Kudos

Dear Experts,

we have two plants, one is Production plant-Plant A and Sales plant - Plant B. we have estimated Cost in Plant A for a FG material  and updated the price in Material Master also. Now my Confusion is, Did we update the Same price for the same Material in Plant B (sales plant) and for this which configuration should we maintain,,

Thanks in Advance,,

rgds,

ravi 

Accepted Solutions (0)

Answers (1)

Answers (1)

kamalkumar_biswas2
Active Contributor
0 Kudos

Hi Ravi

Yes you can do..follow the steps:

1. Extend same material to receiving plant in MM01

2. Create spl procurement key in OMD9 for stock transfer and assign in Material Master in Receiving plant MRP 2

3. In costing variant define Transfer control PC04 (current std cost)

Now when you run cost estimate in sending/producing plant the same cost will flow/update in receiving plant

kamal