Table or tables connection to get project actual cost with posting date

All PS Experts,

Kindly help getting the table or tables connection to get the project actual cost with posting date.

Suggestion are highly appreciated.

Thanks Indeed.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Oct 17, 2015 at 10:32 AM

    Hi Ankit,

    Check in RPSCO with Value type 4.

    You need to pass the WBS element in PRPS and get the object number. Pass the object number into RPSCO.

    Refer below link for further table distribution.

    SAP PS Tables

    Regards

    Terence