cancel
Showing results for 
Search instead for 
Did you mean: 

Read PP master data in Production Order

Former Member
0 Kudos

Dear all,

I have a requirement where I want to make "Read PP master data mandatory" before posting Production order so that system reads latest BOM. Then whether the Production order is manual or from converted  from planned order it will be essential to use. It will be kind if someone tell what dev is needed in system ,can it be done through some Badi ,message number or what. Early reply will be appreciated.

Regards

Rajeev Gupta

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You should implement the modification note 391846. This note introduces a customizing that allows you to define if the BOM will be exploded during the conversion for your order type.

BR
Caetano