Dear all,
I have a requirement where I want to make "Read PP master data mandatory" before posting Production order so that system reads latest BOM. Then whether the Production order is manual or from converted from planned order it will be essential to use. It will be kind if someone tell what dev is needed in system ,can it be done through some Badi ,message number or what. Early reply will be appreciated.
Regards
Rajeev Gupta
Hello
You should implement the modification note 391846. This note introduces a customizing that allows you to define if the BOM will be exploded during the conversion for your order type.
BR
Caetano