No Pur Req. without source of supply in SNP Optimizer

Hi,

We have a requirement where we do not want Pur Req (external) to be created if source of supply is not maintained when we run SNP optimizer.. Please provide your inputs on this.

We have a setting in version where we can maintain similar setting for planned order.

regards,

Mohit

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 17, 2015 at 07:33 PM

    Hello Mohit,

    You need a custom solution.

    It can be done by using custom program to delete planned orders or Pur Req without source of supply. This program can be run immediately after SNP Heuristics and/or then again after Capacity Leveling.

    You will require this BAPI :  BAPI_MOSRVAPS_DELEMULTI

    Hope this will help.

    Thank you

    Satish Waghmare

    Add comment
    10|10000 characters needed characters exceeded

    • I am guessing that is not the requirement.

      Are you trying to prevent optimizer from creating pur req's with source of supply blank when you have alternate sources of supply that are valid?

      What if there is no valid source of supply?