Selection Variant in CNE2

Dear All,

how to define selection Variant in CNE2 (Tcode) collective Processing.

     Actually I Create a Selection Variant for 20 Selected Projects. by tick on Only for background processing and save the variant. and then I run the project progress. but it give 0 in CNE5 project progress. while when i run CNE1 for these projects it shows progress.

Thanks

Govind

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Oct 17, 2015 at 10:36 AM

    Hi Govind,

    You need to check the Progress Version /Period are correct in the variant. May be the period is incorrect, kindly check it.

    Did you execute the CNE1 with the same period for which you used in CNE2?

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Govind,

      I tried to execute for multiple projects, i am able to get the output.

      Below is the Selection Variant I have saved

      You need to check the period executed in CNE1 and CNE2, if this is the issue again, then you need to contact SAP.

      Regards

      Terence

      Capture.JPG (40.0 kB)
  • Oct 19, 2015 at 12:15 PM

    HI Govind

    variant is nothing but its data saved in selection input screen, now let you know how to create this before executing the business transaction save the selection input then system will ask variant name and description give and save.

    so purpose of variant creation multiple user can use simultaneously same variant.

    Regards,

    Sanjeev

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Snajeev,

      Thanks for the Reply.

      Actually I've created the Selection Variant, but after Updation of Progress (through CNE2 and this Variant), Actual NAggPlP and ANAgAct showing 0. while it would be showing some value.