MRP terminating for one material

0 Kudos


Hi,

MRP background job working fine without any error messages. But for one material which is having MRP Type V1 getting terminated with message 8 which can see in MRP spool.  Please suggest why it is terminating.

BR,

sam

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member189817
Active Contributor
0 Kudos

Hello

  Please share the screen shot of MD05 for that material.

It could be also  because of Factory calendar as it can be long lead time material.So please also check the Factory calendar. (Because as we are in year end I suspecting it as one of the reason)

Regards,

Velmurugan S

0 Kudos

Hi,

Checked in MD05. The last MRP run occured on 14th Oct.  Want to know why failed on 15th & 16th .

BR..

Sam

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

What happens if you try to plan this material on MD03 or MD43?

Regards
Caetano

0 Kudos

Hi Caetano,

Thanks for your response. Tried to run MRP using MD02 , it look ok. In MD05 the last MRP run shown as today's date also planning file entries creation date updated in table DBVM with today's date. The issue is with background job only. System terminating this material with message 8. Could you please through some light on this?

BR,

Siva

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Try to check if this material appears on report RMMDERRO.

0 Kudos

Hi Catetano,


Material not appearing in report RMMDERRO.Pl let me know if there is any otherway of checking.


BR,

sam

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

That does not make sense to me.

If a termination is still happening during the MRP run, you should be able to see an error on transaction MD05 or RMMDERRO.

BR
Caetano

0 Kudos

Hi Caetano,

The material MRP type is V1. Also the planning file entries table DBVM not updating with date.

BR,

sam

0 Kudos

Hi Caetano,

If I create planning file entry manually, on that day system considering for MRP run in background job. Next day system not considering for MRP run. Please suggest. Is there any way to create planning file entry permanently rather than daily.

BR,

sam

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

The planning file flags are checked automatically after each MRP relevant change for a material. If you want to ensure that all the materials will be planned, then you must run MRP with key NEUPL.

michael_kozlowski
Active Contributor
0 Kudos

Hi,

check the MRP 1 - MRP 4 tabs in material master data. Some parameters seems to be missing.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello


You can find details about the termination on the MRP list (transaction MD05). See the blog  which explains why it's so important to use this transaction to analyze the MRP results.



Regards
Caetano